The construction of Koysha Hydroelectric Power Project is being expedited thanks to the special attention given by the government to mega projects in Ethiopia, according to the FDRE Government Communication Service.
Minister of State for Communications, Selamawit Kassa, said that the construction of the Koysha hydropower dam is progressing very well following the government’s move to address the challenges that were dragging the construction of this project.
Meanwhile, the project’s deputy manager Mr. Abayneh Getnet has announced that the total construction of the project has reached over 60 percent.
To mark the World Tourism Week, the FDRE Government Communication Service, in collaboration with the Ministry of Tourism, is conducting a media tour of the South West Region, which is blessed with tourism potential.
It is said that Koysha Hydropower Project is one of the destinations of the media tour.
The Minister of State Ms. Selamawit asserted that the government’s commitment in rectifying the challenges of the country’s mega projects and accelerating their construction is part of the ongoing nationwide reform works.
The current progress of the Koysha hydropower dam construction is a manifestation to this commitment, according to the Minister of State.
The Deputy Manager of the project, Abayneh Getnet, said that the issues that were holding back the construction of Koysha hydroelectric plant have been rectified and the construction is going well now.
It is learned that the construction of the project is being carried out by “We Build”, formerly known as Salini. The manager of the project, Eugenio Zopis, said that when the construction of the Koysha hydropower dam is completed, it will have the capacity to generate 1800 megawatts of power with 6 power station turbines.
Blessed with natural scenery, the area is a major producer of honey, fruits and spices where the roads built as part of the project have benefitted the local community by creating market linkages, it was stated.
It is indicated that the project has currently created job opportunities for more than 4,500 citizens, of which 30 percent of them are local youth.
“Koysha” Hydroelectric Power Project
Koysha (2’160 MW, under construction) is the fourth hydropower plant of Omo/Gibe river cascade in Ethiopia, comprising Gilgel Gibe (200 MW), Gibe II (420 MW) and Gibe III (1’870 MW), all currently in operation.
Koysha is a step forward in the development of the entire hydropower potential of the Omo river and represents a realization of the large-scale vision started more than 25 years ago with the design of Gilgel Gibe hydroelectric power plant. It testifies our long-term commitment for the progress of Ethiopia’s energy sector.
The project includes several outstanding examples of value engineering and design optimization, carried out by SP throughout the entire design and construction period of the hydroelectric power plant.
The layout includes an RCC gravity dam, approximately 180 m high, that creates a large reservoir of about 6’500 Mm3.
Floods are discharged by means of a gated spillway located on a saddle at the left side of the RCC dam: a large channel with a flip bucket designed for releasing a flow of about 13’100 m3/s in a plunge pool adjacent to the river, downstream of the powerhouse.
The dam is crossed by three steel penstocks feeding an open-air powerhouse, one of the intakes is lowered to allow early generation using the first two units during the first impounding.
The project includes two 6 m diameter middle level outlets embedded in the dam body allowing to control the reservoir level during the first impounding, release artificial/ecological flows and lowering the reservoir level for inspection/maintenance needs.
The river diversion layout includes two concrete culverts on the right side of the river, aimed to divert the river during the dam construction and designed to discharge up to 3’000 m3/s, and an upstream composite RCC/rockfill cofferdam.
Both the river diversion layout and the energy-generation operating rules of Koysha have been optimized taking advantage of the large flow regulation capacity of the upstream Gibe III project.
Tandem operations of the two projects allow to maximize energy generation and provide great flexibility guaranteeing power supply during both dry season and peak-demand period.
The power house is located on the left side of the river, housing eight Francis turbines generating 2’160 MW, together with erection bays and control building. Step-up transformers are located behind the powerhouse. Each unit is connected to three single-phase 400 kV transformers, for a total of 24 transformers that are linked through overhead lines to the 400kV Switchyard.